Works on bypass around Belgrade as of spring

Works on the cloverleaf interchange Batajnica 3.9 km long and Dobanovci-Batajnica road 6.1 km long on the route of the bypass around Belgrade will commence in spring.

Supported by

The company Koridor 10 states that the works on Strazevica tunnel are also expected to continue.

– During this year, works will be commenced on construction of bridges in B5 sector – between Orlovaca and Strazevica tunnel, and activities will be continued in B6 sector – between Strazevica and Bubanj Potok – reads the statement.

The job of construction of Batajnica cloverleaf interchange has been won by the companies Planum and Ratko Mitrovic and they should finish it in 730 days. Strabag will also be working on construction of the bypass around Belgrade, from Dobanovci to Batajnica, and it will also have 730 days to finish the job.

Supported by

Works on Strazevica tunnel, 750 meters long, are being carried out by Energoprojekt and the job should be finished untl July 31.

Construction of three bridges on the section between Orlovaca and Bubanj Potok will commence in March and should be finished in 540 days, reads the statement.

Suppported byOwner's Engineer

Building permits in Serbia drop by 16.3% in November 2024

In November 2024, Serbia saw a decline in building permits issued, with a total of 2,811 permits granted, marking a 16.3% decrease compared to...

Serbia and UAE explore joint robotics program to harness Serbian engineering potential

Serbia and the United Arab Emirates (UAE) are exploring the possibility of launching a joint program in the field of robotics, aiming to leverage...

Serbia tackles challenges from US sanctions on Russian oil fleet, focuses on ensuring oil supply stability

Tomislav Mićović, Secretary General of the Association of Oil Companies, recently discussed the impact of new American sanctions on the Russian fleet of shadow...
Supported byspot_img
Supported byspot_img
Supported byspot_img
error: Content is protected !!